Access Road Installed

The access road to the 19 acres of property owned by Avery for the construction of a larger facility is complete.  The project involved excavating the road surface, installling utilities including water, gas and electric, as well as a fire hydrant.  The base of the road is gravel and will be paved after the church building has been constructed.  An anonymous donor has pledged to fund the construction costs of the access road and excavation of the new church site.

  Civil Engineering Complete

The church's civil engineer, CTL Engineering, Inc., has completed the site plans for the new Avery.  The plans show how the earthmoving needs to be completed, where retention walls need to be constructed, where parking areas will be installed, and how drainage on the site will function.  These plans were completed on January 17, 2004.  This is a significant step in moving the project forward.

 

 

  Excavation Nearing Completion

The excavation for the new church site is nearing completion!  Several months of hard work have gone into the development of the 19 acres of real estate.  

 

  Avery Coming Together Spiritually (ACTS)

To fund the Avery Vision Program, a stewardship event termed ACTS - Avery Coming Together Spiritually - was developed. Thank you to all who have contributed their time and resources to our Vision project.